Most of the time on an extension goes on approvals, not building. Planning takes up to 8 weeks, prior approval up to 42 days and party wall notice up to two months, but you can run all three at once. The build itself depends on size and spec, so ask for a build programme with your quote.
Last updated November 2026

MTR quotes come back within 3 to 5 working days of the site visit and stay valid for 30 days. We call you about a week after you receive yours, in case you have questions.
Once you accept a quote, you need drawings. A single storey extension needs a plan and elevations for building control, and for planning if you apply. If you're knocking through, a structural engineer sizes the steel beam at the same stage. The faster you settle the layout, the faster drawings come back. Changing the design after drawings start sends them round again.
It depends which route your extension takes:
| Route | Time | Source |
|---|---|---|
| Permitted development | No application needed | Planning Portal |
| Prior approval for a larger extension | Up to 42 days | GPDO |
| Householder planning application | Most within 8 weeks | GOV.UK |
| Building regulations, full plans | Five weeks, or up to two months if you agree | Planning Portal |
| Party wall notice | One or two months | Explanatory booklet |
Not sure which planning route applies? Read do you need planning permission for an extension.
Yes. Once your drawings are final, submit building control and serve party wall notice while planning runs. Building regulations approval lasts three years from when you deposit the plans (Planning Portal), so nothing goes stale while you wait for planning. See party wall agreements: when you need one and what it costs for the notice rules.
| Stage | What happens |
|---|---|
| Groundworks | Dig and pour foundations, lay drains. Building control inspects. |
| Walls | Brickwork up to roof level. |
| Roof, windows and doors | The room becomes weathertight. |
| Knock through and first fix | Steel goes in, the old back wall comes out, cables and pipes go in. |
| Plaster and second fix | Walls plastered, sockets, lights and radiators fitted. |
| Finishing | Flooring, kitchen, decorating. Building control signs off. |
Building control inspects at set stages, usually foundations, drainage and completion.
Illustration only. This is not a past MTR job.
You want a 5 metre kitchen extension on a semi in Northfield. That's past the 3 metre permitted development limit, so you go for prior approval.
Running everything side by side saves you weeks compared with doing each approval in turn.
Building control carries out a final inspection and issues a completion certificate. Keep it with your house deeds, because a buyer's solicitor will ask for it. Keep your lawful development certificate or planning decision with it, and any party wall award.
Lead times. Bifold doors, roof lanterns and kitchens are made to order. Order them when you sign, not when the walls go up.
Ground surprises. A drain in the wrong place or soft ground means redesigned foundations and another visit from building control.
Weather. Heavy rain and frost stop bricklaying and concrete pours.
Changes mid build. Moving a door or switching the kitchen layout after the walls go up costs you time as well as money.
Paul runs one or two jobs at once, so your build keeps the same team from groundworks to handover. Your start date depends on what's already booked when you sign, so ask about it when you get your quote.
Costs follow the same stages as time. See our extension cost guide and loft conversion cost guide.
Lofts often skip planning under permitted development, so the paperwork can be shorter. The build still includes stairs and steelwork.
On a full plans application you can, but any work that doesn't match the approved plans may need changing. We wait for approval.
Spring and summer suit groundworks and brickwork. Inside work carries on through winter once the room is weathertight.
Most people do. The disruptive part is the knock through into the house, which comes once the new room is weathertight.
It adds a council decision to the process, usually within 8 weeks. You can build without one under permitted development, but most people apply so they have written proof for a future sale.
Run your numbers through the cost calculator, or ask for a free quote. Quotes come back within 3 to 5 working days and stay valid for 30 days.