Guide · Extensions

How long does an extension take, from first quote to finished build

Most of the time on an extension goes on approvals, not building. Planning takes up to 8 weeks, prior approval up to 42 days and party wall notice up to two months, but you can run all three at once. The build itself depends on size and spec, so ask for a build programme with your quote.

Last updated November 2026

How long does an extension take?: MTR Developments guide illustration

How long does it take to get a quote?

MTR quotes come back within 3 to 5 working days of the site visit and stay valid for 30 days. We call you about a week after you receive yours, in case you have questions.

What happens between the quote and the drawings?

Once you accept a quote, you need drawings. A single storey extension needs a plan and elevations for building control, and for planning if you apply. If you're knocking through, a structural engineer sizes the steel beam at the same stage. The faster you settle the layout, the faster drawings come back. Changing the design after drawings start sends them round again.

How long does planning take?

It depends which route your extension takes:

RouteTimeSource
Permitted developmentNo application neededPlanning Portal
Prior approval for a larger extensionUp to 42 daysGPDO
Householder planning applicationMost within 8 weeksGOV.UK
Building regulations, full plansFive weeks, or up to two months if you agreePlanning Portal
Party wall noticeOne or two monthsExplanatory booklet

Not sure which planning route applies? Read do you need planning permission for an extension.

Can approvals run at the same time?

Yes. Once your drawings are final, submit building control and serve party wall notice while planning runs. Building regulations approval lasts three years from when you deposit the plans (Planning Portal), so nothing goes stale while you wait for planning. See party wall agreements: when you need one and what it costs for the notice rules.

What are the stages of the build?

StageWhat happens
GroundworksDig and pour foundations, lay drains. Building control inspects.
WallsBrickwork up to roof level.
Roof, windows and doorsThe room becomes weathertight.
Knock through and first fixSteel goes in, the old back wall comes out, cables and pipes go in.
Plaster and second fixWalls plastered, sockets, lights and radiators fitted.
FinishingFlooring, kitchen, decorating. Building control signs off.

Building control inspects at set stages, usually foundations, drainage and completion.

What does a typical timeline look like? (illustration)

Illustration only. This is not a past MTR job.

You want a 5 metre kitchen extension on a semi in Northfield. That's past the 3 metre permitted development limit, so you go for prior approval.

  • Week 1: site visit, and your quote arrives 3 to 5 working days later.
  • Weeks 2 to 4: you accept, drawings get done, the engineer sizes the steel.
  • Week 4: you submit prior approval, building control plans and party wall notices on the same day.
  • Weeks 4 to 10: the council has 42 days on prior approval. Building control decides inside five weeks. Party wall notice runs its course.
  • Week 10 onwards: work starts on the date agreed in your quote.

Running everything side by side saves you weeks compared with doing each approval in turn.

What happens at the end of the build?

Building control carries out a final inspection and issues a completion certificate. Keep it with your house deeds, because a buyer's solicitor will ask for it. Keep your lawful development certificate or planning decision with it, and any party wall award.

What slows an extension down?

Lead times. Bifold doors, roof lanterns and kitchens are made to order. Order them when you sign, not when the walls go up.

Ground surprises. A drain in the wrong place or soft ground means redesigned foundations and another visit from building control.

Weather. Heavy rain and frost stop bricklaying and concrete pours.

Changes mid build. Moving a door or switching the kitchen layout after the walls go up costs you time as well as money.

Why does MTR run only one or two builds at a time?

Paul runs one or two jobs at once, so your build keeps the same team from groundworks to handover. Your start date depends on what's already booked when you sign, so ask about it when you get your quote.

Costs follow the same stages as time. See our extension cost guide and loft conversion cost guide.

Good to know

Questions people ask.

Lofts often skip planning under permitted development, so the paperwork can be shorter. The build still includes stairs and steelwork.

On a full plans application you can, but any work that doesn't match the approved plans may need changing. We wait for approval.

Spring and summer suit groundworks and brickwork. Inside work carries on through winter once the room is weathertight.

Most people do. The disruptive part is the knock through into the house, which comes once the new room is weathertight.

It adds a council decision to the process, usually within 8 weeks. You can build without one under permitted development, but most people apply so they have written proof for a future sale.